Status & Plan

Year Phase Land Factory and Stock area Machinery Production based on 10 hrs working Equipment Production Feed Stock Supply Status
Total (sq.m) Total (sq.m) Maximum Capacity Total (Ton) Tons/Year Equipment Brand Capacity Status Start Outsource Dried base Contract Farming, dried Own Plantation, dried
Total 102,400 90,528 648,000 324,000 /Origin *Quantity Area/Size Area/Size Area/Size
Phase 1
Year 2015
Phase 1 34,133 31,776 216,000 108,000 50km radius from Factory Chachoengsao, Prachinburi, Sakaeo
120,000 ton/year
Starting Factory Building, Installation and Commissioning completed
1st Line 34,133 12,192 72,000 36,000 Saw dust Machine Serim/Korea 15 tons/hr Installed 2-May-15
Dryer Sen Yang/China 7 tons/hr *1 Installed
Pelletizer Yong Li/China 2.5 tons/hr *3 Installed
Huan Tai/China 1 ton/hr *1 Installed
Cooling & Packing Yong Li/China L/S Installed
2nd Line 9,792 72,000 36,000 Saw dust Machine Serim/Korea 15 tons/hr Delivery 30 Jun 2015 1-Sep-15 Building completed. All of equipment has been purchased and installation will be finished before Aug 2015.
Dryer Yong Li/China 5 tons/hr *1
Pelletizer Jinwoo/China 1 ton/hr *6
Huan Tai/China 1 ton/hr *2
Cooling & Packing Jinwoo/China L/S
3rd Line 9,792 72,000 36,000 Saw dust Machine Serim/Korea 15 tons/hr Delivery 31 Aug 2015 1-Dec-2015 Building completed. All of equipment has been purchased and installation will be finished before Oct 2015.
Dryer Sen Yang/China 7 tons/hr *1
Pelletizer Jinwoo/China 1 ton/hr *6
Cooling & Packing Jinwoo/China L/S
Phase 2
2016
Phase 2 34,133 29,376 216,000 108,000 50km radius from Factory Chachoengsao, Prachinburi, Sakaeo
200,000 ton/year
40,000 tons/year Starting Total 240,000 tons/year for 2 phases
4th Line 34,133 9,792 72,000 36,000 All of Equipment Mar-16 2-May-16
5th Line 9,792 72,000 36,000 All of Equipment Jun-16 1-Sep-16
6th Line 9,792 72,000 36,000 All of Equipment Sep-16 1-Dec-16
Phase 3
2017
Phase 3 34,133 29,376 216,000 108,000 50km radius from Factory Chachoengsao, Prachinburi, Sakaeo
200,000 ton/year
120,000 tons/year 30,000 tons/year Total 350,000 tons/year for 3 phases
7th Line 34,133 9,792 72,000 36,000 All of Equipment Mar-17 2-May-17
8th Line 9,792 72,000 36,000 All of Equipment Jun-17 1-Sep-17
9th Line 9,792 72,000 36,000 All of Equipment Sep-17 1-Dec-17